GC-59
 
PARTIAL ACCEPTANCE NOT FINAL

The acceptance of portions of the Works from time to time for the purposes of making partial payments or progress payments shall not be considered as final acceptance. Unless accepted in writing by NIA all such portions of the Works covered under the said partial payments shall still be under the responsibility of the Contractor. As such, Contractor is still liable to maintain and care for said part of the Works. In case any damage, loss or injury shall happen to the Works or any part thereof, from any cause whatsoever except for Special Risks as defined on Article GC-8, while the Contractor shall be responsible for the care thereof, the Contractor shall, at his own expense, repair and make good the same, so that at completion the Permanent Works shall be in good order and condition in conformity in every respect with the requirements of the Contract.