Make your own free website on Tripod.com
GC-48
 
CONSTRUCTION EQUIPMENT AND TOOLS

All construction equipment and tools to be used for the Contract Work shall be furnished by the Contractor. The Contractor shall submit to NIA a complete list of all brand new and/or reconditioned and good running condition equipment that he requires in connection with this Contract Work. The Contractor shall prepare subsequently a schedule of delivery for the said equipment based on the approved construction schedule and program. No separate payment shall be made included in the bid prices for the various items in the Bill of Quantities.