CONTRACTOR'S RIGHT TO TERMINATE CONTRACT WORK
 
If the Contract Work shall be completely stopped for a continuous period of more than 90 calendar days through no act or fault of the Contractor or anyone employed by him or as a result of the occurrence of Special Risks as provided in Article GC-8, LIABILITY FOR SPECIAL RISKS, Contractor shall, without prejudice to any other right or remedy, have the right to give NIA 15 calendar days written notice to the effect that the Contractor intends to terminate the Contract if the Contract Work cannot be resumed by Contractor.

If within 15 calendar days after receipt by NIA of such notice, Contractor cannot resume Contract Work for reasons specified above, he (Contractor) shall have the right to terminate the Contract and recover from NIA payment for any loss or damage to the Contract Work arising out of, or in connection with, or by consequence of such termination as described in Article GC-24, PAYMENT IF CONTRACT IS TERMINATED.